Now that the apartment in which the boys will stay is almost complete, work has continued on the remaining three apartments.

All of the electrical work including installation of air conditioners in the bedrooms and fans is complete. Toilets, washbasins and showers are all complete and functioning.

Gas tanks have been installed and filled with gas. Aluminium doors have been installed on the outside bathrooms and at the rear of each apartment.

The old stove from Refugio Mazatlan was cleaned up by the boys and then moved into one of the apartments along with a donated fridge .

The boys have also started painting the remaining apartments and they are looking quite good.

The remaining work is to install the closets, complete the paintwork. and do a final and thorough clean.